Micron Project Tracker

ITM0NKEY / THE CLAY CHRONICLE

Micron Clay Project timeline

From announcement to a four-fab campus.

THE STORY, MILESTONE BY MILESTONE19 milestones

Scroll to explore. Use category filters to focus the story. Milestones are evenly spaced, not a scale of elapsed time.

  1. 2022
    Community

    October 4, 2022

    Micron chooses Clay

    Micron announces plans for a Clay megafab, with up to $100 billion in investment over more than 20 years.

    CompletedConfidence: Confirmed
  2. 2023
    Community

    April 28, 2023

    Community voices take a seat

    New York and Micron announce the Community Engagement Committee to guide local priorities and community investment.

    CompletedConfidence: Confirmed
  3. 2024
    Workforce

    April 25, 2024

    Preparing the workforce

    Upstate New York is announced as a National Workforce Hub, supporting regional preparation for semiconductor and advanced manufacturing jobs.

    CompletedConfidence: Confirmed
  4. 2024
    Community

    July 18, 2024

    Community fund takes shape

    New York releases guidelines for the $500 million Green CHIPS Community Investment Fund, covering workforce, education, housing and community priorities.

    CompletedConfidence: Confirmed
  5. 2024
    Community

    December 10, 2024

    CHIPS award finalized

    Commerce finalizes up to $6.165 billion in funding for Micron’s Idaho and New York projects. Payments depend on project milestones; this is not a Clay-only award.

    CompletedConfidence: Confirmed
  6. 2025
    Permits

    December 12, 2025

    State resource permits issued

    DEC issues the project’s freshwater wetlands, water-quality certification and incidental-take permits. This milestone does not mean every project permit is complete.

    CompletedConfidence: Confirmed
  7. 2025
    Permits

    December 16, 2025

    Federal review reaches a decision

    The CHIPS Program Office completes its environmental Record of Decision, approving federal funding disbursements under the project award’s terms.

    CompletedConfidence: Confirmed
  8. 2026
    Construction

    January 16, 2026

    Ground is broken

    Micron holds the official groundbreaking for its Clay megafab, marking the start of the campus construction chapter.

    CompletedConfidence: Confirmed
  9. 2026
    Utilities

    March 23, 2026

    Water service permits issued

    DEC issues wetlands and water-quality approvals for water services to White Pines Commerce Park. Permit issuance does not establish construction completion.

    CompletedConfidence: Confirmed
  10. 2026
    Permits

    March 31, 2026

    Air permit issued

    DEC issues the Title V air permit for emissions from Fab 1 and Fab 2 operations. The permit is an approval, not a production-start milestone.

    CompletedConfidence: Confirmed
  11. 2026
    Utilities

    April 10, 2026

    Wastewater expansion permitted

    DEC issues the Oak Orchard wastewater treatment plant’s discharge-permit renewal and modification for a phased capacity increase.

    CompletedConfidence: Confirmed
  12. 2026
    Construction

    July 9, 2026

    First concrete is poured

    Micron celebrates the first concrete pour at Clay and reports the transition from early site preparation to vertical construction.

    CompletedConfidence: Confirmed
  13. 2026
    Transportation

    August 12, 2026

    Rail siding permits issued

    DEC issues wetlands and water-quality approvals associated with rail siding track. This confirms permitting, not completion of the rail infrastructure.

    CompletedConfidence: Confirmed
  14. 2026
    Permits

    September 28, 2026

    Review agreement amended

    NIST records completion of the first amendment to the Micron project’s Programmatic Agreement.

    CompletedConfidence: Confirmed
  15. TODAY
  16. 2030
    Construction

    2030 • Micron target

    Fab 1 production target: 2030

    Micron’s January 2026 announcement says production is expected to start in 2030, with the fabs ramping through the decade. This is a target, not a completed milestone or guaranteed date.

    UpcomingConfidence: Confirmed
  17. 2033
    Construction

    2033 • planning estimate

    Fab 2 planned completion

    The federal Record of Decision’s main project description estimates Fab 2 completion in 2033. This is a planning estimate, not a confirmed production start or guaranteed delivery date.

    EstimatedConfidence: Estimated
  18. 2037
    Construction

    2037 • planning estimate

    Fab 3 planned completion

    The federal Record of Decision’s main project description estimates Fab 3 completion by the end of 2037. Equipment readiness, initial production and full output are distinct milestones.

    EstimatedConfidence: Estimated
  19. 2041
    Construction

    2041 • planning estimate

    Fab 4 and campus build-out

    The federal Record of Decision’s main project description estimates Fab 4 completion in 2041. Completion of the four-fab build-out is followed by the ramp to full production.

    EstimatedConfidence: Estimated
  20. 2045
    Construction

    2045 • planning estimate

    All four fabs: full production

    The federal Record of Decision projects the four-fab campus reaching full production output by 2045. This is the long-range build-out and production-ramp endpoint, subject to changes in approvals, demand and execution.

    EstimatedConfidence: Estimated
Completed In Progress Upcoming Estimated
How to read confidence badges

Confirmed: supported by an official primary source. Observed: documented direct observation. Reported: attributed to a published report. Estimated: inferred timing or sequencing. Status describes progress; confidence describes the evidence. Neither implies the whole project is complete.